The
project initially involved performing a KYPIPE analysis and system study
to determine the necessary waterline size and available flows and
pressures needed to serve the project area. It helped determine the
potential need for elevated storage and booster pumping. The study
encompassed an area beyond the immediate design limits so future system
expansion could be readily accommodated. This project will receive
water from the new Green County southerly wellfield. After the study
was performed the waterline was designed involving approximately two miles
of waterline, a river crossing and right of way acquisition.
Also an engineer's opinion of probable cost and PTI were prepared.
Coordination with OEPA and the Miami Conservancy District were necessary. |